Jan. 11, 2025
The amount of silicon manganese furnace electrodes lowered each time is 20mm. When rushing to release the electrode, each silicon manganese furnace should lower it once every 40 minutes according to the situation of the furnace, and each time should not exceed 20mm, and the hourly power consumption should be guaranteed. When selecting, you must confirm before placing the electrode to prevent misoperation.
After loosening the upper ring and lifting, you must return to zero first, and then loosen the lower ring after the upper ring is fixed. Continuous operation is not allowed.
It is not allowed to loosen the water jacket and directly release the electrode. When the electrode is difficult to place, you can move the water jacket first, and then tighten it before releasing it.
When the current changes suddenly, the operator has the right to directly open the switch. Before placing the electrode in the silicon manganese furnace, knock the electrode with a wooden pole to check whether it is suspended.
Latest News
1 Ton Electric Arc Furnaces For Cast Iron
Jan. 10, 2025
Induction Melting Furnace For Aluminium Principle and Use
Jan. 08, 2025
Latest Products
Customized metallurgical machinery and equipment range: Electric Arc Furnace, Submerged Arc Furnace, LF Refining Furnace, Vacuum Furnace, Induction Furnace, Dust Remove System, Water Treatment Equipment, etc. Providing the most advanced equipment integration services, metallurgical equipment can be customized according to different needs of customers, and production capacity can be adjusted according to customer requirements.
Electric Arc Furnace
Submerged Arc Furnace
LF Refining Furnace
VD / VOD Vacuum Refining Furnace
Induction Furnace
Furnace Accessories
Navigation
E-mail: anna@srfurnace.com
Tel: +86 159 2955 5868
WhatsApp: +86 159 2955 5868
Add:
Room 102, Building 7A, Free Trade Xintiandi, Fengdong Avenue, Fengdong New Town, Xi'an City, Shaanxi Province